2003 – I-70 / Lake St. Louis Boulevard Bridge
State: MO
Year: 2003
Owner: State
Location: Urban
Beam material: Concrete
Spans: Two-span
Max Span Length (ft.): 67
Total Bridge Length (ft.): 134
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
value engineering
Geotechnical Solutions:
Structural Solutions: adjacent box beam, MSE wall,
grouted key closure joint

2003 – I-405 / Northeast 8th Street Bridge
State: WA
Year: 2003
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 164
Total Bridge Length (ft.): 328
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide
Project Planning: design-bid-build,
incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: FDcBs (Full-width concrete-decked steel beam unit),
CIP reinforced closure joint

2003 – Church Street Bridge
State: CT
Year: 2003
Owner: City of New Haven
Location: Urban
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 320
Total Bridge Length (ft.): 1274
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Other ABC Method
Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Truss span w/o deck,

2003 – Carquinez Strait Bridge (Al Zampa Bridge)
State: CA
Year: 2003
Owner: State
Location: Urban
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 2389
Total Bridge Length (ft.): 3465
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Steel orthotropic box girder span, Precast cap shells,

2002 – US 26 Bridge over Mill Creek
State: OR
Year: 2002
Owner: State
Location: Rural
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 265
Total Bridge Length (ft.): 536
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional
Project Planning: State process,
design-bid-build,
full lane closure
Geotechnical Solutions:
Structural Solutions: Exodermic deck,
CIP reinforced concrete closure joints, asphalt overlay w/o membrane

2002 – SH 86 Bridge over Mitchell Gulch
State: CO
Year: 2002
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 40
Total Bridge Length (ft.): 40
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, lane rental, value engineering
Geotechnical Solutions:
Structural Solutions: adjacent slab beam, precast abutment cap, precast abutment stem, precast wingwall,
PT ducts/bonded, asphalt overlay w/membrane, prefabricated railing

2002 – I-10 Bridge over Lake Pontchartrain (original Twin Spans)
State: LA
Year: 2002
Owner: State
Location: Urban
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 65
Total Bridge Length (ft.): 65
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Other ABC Method
Project Planning: design-bid-build,
full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: FDcBc (Full-width concrete Decked concrete Beam unit),
CIP reinforced closure joint

2001 – MD Route 24 Bridge over Deer Creek (Rocks Steel Truss Bridge)
State: MD
Year: 2001
Owner: State
Location: Rural
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 122.5
Total Bridge Length (ft.): 122.5
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: FRP deck panel,
CIP reinforced closure joint, grouted blockout w/shear connector, asphalt overlay w/o membrane

2001 – Keaiwa Stream Bridge
State: HI
Year: 2001
Owner: State
Location: Rural
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 34
Total Bridge Length (ft.): 230
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: adjacent slab beam,
grouted key closure joint

2001 – Illinois Route 29 Bridge over Sugar Creek
State: IL
Year: 2001
Owner: State
Location: Rural
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 67.2
Total Bridge Length (ft.): 253.1
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
Geotechnical Solutions:
Structural Solutions: full-depth precast deck panel w/PT,
CIP reinforced closure joint, micro-silica concrete overlay